Drusilla Ln (Jefferson Hwy - Old Hammond Hwy) Project Page

Project Description: This project proposes to provide access management and turning lane improvements along Drusilla Ln. This project is also proposed to enhance pedestrian and bicycle mobility.

Council District: 11

Project Type: Improve Existing Corridors

Current Phase: Planning

Design Consultant: TBD

Project Manager: STANTEC

Current Cost Estimate ($M): $8.00

Estimated Letting Date: 2030

Project Updates

Date Status
11/2025 This project is in the planning phase based on prioritization. Expecting contract procurement and design phase initiation in 2026.
10/2025 This project is in the planning phase based on prioritization. No design activity is underway.

Documents