Harding At I-110 Project Page

Project Description: Additional turn lane storage length, improved safety, and enhanced access to I-110 will be included in the ramp terminal intersection improvements.

Council District: 2

Project Type: New Capacity

Current Phase: Planning

Design Consultant: Neel-Schaffer

Project Manager: Kahli Cohran

Proposition Budget: $5,000,000

Estimated Letting Date: 2032

Project Updates

Date Status
09/2023 The Design Consultant has completed the Traffic Study for the Harding @ I-110 project. With the realignment of Plank Road near the airport, traffic in this area is expected to change. This project is on-hold until the traffic responds to the changes and additional information regarding capacity needs can be identified.
01/2023 The Design Consultant has completed the Traffic Study for the Harding @ I-110 project. With the realignment of Plank Road near the airport, traffic in this area is expected to change. This project will go on-hold until the traffic responds to the changes and additional information regarding capacity needs can be identified.
02/2022 The Design Consultant is preparing the Traffic Study for the Harding @ I-110 project.
10/2021 The Design Consultant has begun collecting Traffic Data for the Harding @ I-110 project.
04/2021 The Design Consultant and MOVEBR team are working with DOTD to determine the best way to collect traffic data given the change in patterns due to COVID-19 restrictions, as well as an upcoming DOTD re-striping project that will change patterns in the project area.
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant.

 