Jones Creek Rd (Jefferson to Airline) Project Page

Project Description: Design and construction of a new suburban four-lane roadway with complete streets facilities and green infrastructure elements.

Council District: 9

Project Type: New Capacity

Current Phase: Design

Design Consultant: Sigma Consulting Group

Project Manager: Daniel Marks

Proposition Budget: $5,700,000

Estimated Letting Date: August 2024

Project Updates

Date Status
01/2024 Final design plans are in development. The right-of-way acquisition process has progressed, with most of the slated properties already acquired. Following acquisition of the right-of-way, utility relocation will commence along with a construction project to clear the project corridor and allow for settlement to occur. The roundabout at Jefferson will be constructed separately and before the remainder of the corridor.
12/2023 Final design plans are in development. The right-of-way acquisition process has progressed, with some of the slated properties already acquired. Following acquisition of the right-of-way, utility relocation will commence along with a construction project to clear the project corridor and allow for settlement to occur. The roundabout at Jefferson will be constructed separately and before the remainder of the corridor.
06/2023 Final design plans are in development. The right-of-way acquisition process is underway with agents contacting affected property owners for appraisals and to make offers.
12/2022 Final design plans are progressing. The LADOTD Traffic Study is currently underway to determine the intersection type at Airline Highway. The Right-of-Way acquisition process has been initiated.
06/2022 This project is currently in final design. An LADOTD Traffic Study is currently underway to determine the intersection type at Airline Highway.
11/2021 This project is currently in final design with the exception of the Airline Highway intersection.A traffic study is being conducted to determine the Airline Highway intersection type in collaboration with LADOTD.
07/2021 This project is currently in final design with the exception of the Airline Highway intersection.. A traffic study is being conducted to determine the Airline Highway intersection type in collaboration with LADOTD.
05/2021 The Consultant has submitted the Design Study and progressing to Final Design. A traffic study is being conducted to determine the Airline Highway intersection type in collaboration with LADOTD. A public meeting was held May 4, 2021.
02/2021 A design study is being conducted to identify the alignment and intersection connections for the project. 
11/2020 A design study is being conducted.

 

Documents

Videos

Watch the Virtual Public Meeting Held on May 4, 2021

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.