Jones Creek Rd (Tiger Bend to Jefferson) Project Page

Project Description: Design and construction of a new suburban four-lane roadway with complete streets facilities and green infrastructure elements. The design study was completed under the Green Light Plan program.

Council District: 9

Project Type: New Capacity

Current Phase: Design

Design Consultant: Sigma Consulting Group, Inc.

Project Manager: Justin Schexnayder

Proposition Budget: $13,300,000

Estimated Letting Date: Q1 2023

Project Updates

Date Status
03/2022 Final plans are being developed. Traffic analysis is completed.
05/2021 The project is currently in the final design stage.
05/2021 The Design Consultant has submitted the design study and progressing to Final Design. A public meeting was held May 4, 2021. Traffic analysis for Jefferson High intersection is on-going with a roundabout being the preferred intersection type.
02/2021 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase (anticipated second quarter 2021).
10/2020 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.

 

Documents

Videos

Watch the Virtual Public Meeting Held on May 4, 2021

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.