MacHost (LA 64 to Pride Port Hudson) Project Page

Project Description: This project proposes to improve existing conditions along MacHost Rd including alignment, sight distance, shoulders, and drainage. This project is being designed under the ownership of the City of Zachary.

Council District: 1

Project Type: Corridor Improvements

Current Phase: Right of Way

Design Consultant: PEC

Project Manager: Billy Wall

Proposition Budget: $10,000,000

Estimated Letting Date: April 2024

Project Updates

Date Status
11/2023 Right of way acquisition is underway and offers are being presented to property owners.
11/2023 Design is complete. ROW acquisition ongoing in preparation for utility relocations, clearing & grubbing, and ultimately construction.
12/2022 The Design Consultant has prepared the 90% design plan submittal. Right-of-way acquisition is underway.
05/2022 The 90% design submittal is complete and right of way acquisition is underway. Currently Appraisals are being prepared.
11/2021 The Design Consultant has prepared the 90% design plan submittal and it is currently under review.
07/2021 The Design Consultant is preparing the 90% design plan submittal.
01/2021 The Design Consultant is preparing the Right-of-Way Maps and the 90% design plan submittal.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.