Mickens Rd (Hooper Rd - Joor Rd.) Project Page

Project Description: The planned improvements may include a three-lane section from Hooper Road to Lanier Road with a shared-use path on each side and a closed drainage system. From Lanier Road to Joor Road, the proposed roadway may be two-lanes with a paved shoulder and an open drainage system due to the minimal development in this area.

Council District: 5

Project Type: New Capacity

Current Phase: Design Study

Design Consultant: Evans-Graves Engineers, Inc.

Project Manager: Kahli Cohran

Proposition Budget: $25,000,000

Estimated Letting Date: 2025

Project Updates

Date Status
03/2024 The project is currently in the Design Study phase. The final Design Study report is scheduled to be completed in September 2024.
02/2024 The project is currently in the Design Study phase. The final Design Study report is scheduled to be completed in April 2024.
09/2023 The project is currently in the Design Study phase. The consultant is scheduled to complete a corridor survey in October and begin a traffic analysis in September of 2023. The final Design Study report is scheduled to be completed in March 2024.
08/2023 The project is currently in the Design Study phase. The consultant is scheduled to complete a corridor survey in October and begin a traffic analysis in September. The final Design Study report is scheduled to be completed in March 2024.
01/2023 A design consultant has been selected for the project and a contract is pending execution to begin the design study phase of the project.
12/2020 This project is in the planning phase based on prioritization. No design activity is underway.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.