Nicholson Segment 3 (Parish Line to Gardere) Project Page

Project Description: The proposed project considers a four-lane boulevard section with shoulders, converting the existing two-way travel lanes to the westbound travel lanes. A shared-use path is proposed along the east side of the roadway corridor.

Council District: 3

Project Type: New Capacity

Current Phase: Planning

Design Consultant: TBD

Project Manager: TBD

Proposition Budget: $19,000,000

Estimated Letting Date: 2027

Project Updates

Date Status
12/2020 This project is the planning phase based on prioritization. No design activity is underway.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.