Nicholson Segment 3 (Parish Line to Bluebonnet) Project Page

Project Description: The proposed project considers a four-lane boulevard section with shoulders, converting the existing two-way travel lanes to the westbound travel lanes. A shared-use path is proposed along the east side of the roadway corridor.

Council District: 3

Project Type: New Capacity

Current Phase: Planning

Design Consultant: TBD

Project Manager: TBD

Proposition Budget: $19,000,000

Estimated Letting Date: 2027

Project Updates

Date Status
12/2020 This project is the planning phase based on prioritization. No design activity is underway.

 

Documents

Comments