Old Hammond Hwy Seg 2 (Millerville - O'Neal) Project Page

Project Description: Design and construction to widen Old Hammond Highway to four lanes with a median and sidewalks from Millerville to O'Neal. While final plans were originally completed in 2014, modifications will be made to the plans by the Design Consultant.

Council District: 4, 8

Project Type: New Capacity

Current Phase: Utility

Design Consultant: TRC

Project Manager: Zack Schmidt

Proposition Budget: $18,900,000

Estimated Letting Date: July 2021

Project Updates

Date Status
01/2024 The design engineer is preparing final construction documents and plans. Utility relocations are underway and are expected to be complete once the final right-of-way acquisition is complete. Project will be advertised for construction in 2024 after all right-of-way is acquired.
11/2023 The design engineer is preparing final construction documents and plans. Utility relocations are underway and are expected to continue until the end of 2023 after the final right-of-way acquisition is complete. Project will be advertised for construction in 2024 after all right-of-way is acquired.
09/2023 The design engineer is preparing final construction documents and plans. Utility relocations are underway and are expected to continue until the end of 2023 after the final right-of-way acquisition is complete. Roadway construction will be advertised after all right-of-way is acquired.
07/2023 The design engineer is preparing final construction documents and plans. Utility relocations are underway and are expected to continue until the end of 2023. Roadway construction will follow utility relocations after final Right of Way acquisition is complete.
01/2023 The design engineer is preparing final construction documents and plans. Utility relocations are underway and are expected to continue until the end of 2023. Roadway construction will follow utility relocations.
05/2022 The design engineer is preparing final construction documents and plans. Clearing and grubbing construction has been complete. Utility relocations are underway.
08/2021 The design engineer is working on updating the construction documents and plans.
07/2021 The right-of-way acquisition process is underway. Once the process is complete, clearing and utility relocations will begin followed by construction activities. Clearing and Grubbing is expected to begin in some portions of the project in 4th quarter 2021.
05/2021 The right-of-way acquisition process is underway. Once the process is complete, clearing and utility relocations will begin followed by construction activities.
02/2021 Right of way negotiations are underway. Once right of way acquisition is complete, clearing and utility relocations will begin. 
12/2020 Contracting is underway with the Engineering Design Consultant to begin revisions to the final plans. Appraisals are underway.

Documents

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
Spinks Construction Company Clearing and Grubbing $178,489.16