Pecue Lane (Perkins Rd - Airline Hwy) Project Page

Project Description: I-10 and Pecue Lane interchange construction including the widening of Pecue Lane from Perkins Road to Airline Highway. DOTD will construct all phases of the project including advertisement, contracting and construction engineering and inspection services.

Council District: 9, 11

Project Type: New Capacity

Current Phase: Construction

Design Consultant: Shread-Kuyrkendall & Associates

Project Manager: Brad Ponder

Proposition Budget: $52,000,000

Estimated Letting Date: February 2023

Project Updates

Date Status
09/2024 Construction of Phase III of the project is well underway. Construction is expected through 2025.
04/2024 Phase III is underway which consist of the widened of Pecue Lane, completion of the Diverging Diamond Interchange, interstate ramps, bridges over Ward Creek and connection to Reiger Road.
01/2023 Construction of Phase III of the project has been awarded to the contractor. Construction is expected through 2025.
02/2021 Phase II is under construction. Work continues on the new I-10 overpass bridges.
12/2020 Final right-of-way acquisitions are underway. Final plan revisions are underway. Phase II is under construction, Phase III construction will continue upon completion of Phase II.

 