Perkins Road (Pecue-Siegen) Project Page

Project Description: Design and construction of a widening of Perkins Road from Siegen Lane to Pecue Lane to include pedestrian facilities along the corridor.

Council District: 3, 9

Project Type: New Capacity

Current Phase: Right of Way

Design Consultant: Stantec

Project Manager: Zach Schmidt

Proposition Budget: $26,200,000

Estimated Letting Date: January 2025

Project Updates

Date Status
12/2024 The MOVEBR Perkins Road (Pecue - Siegen) project has achieved a significant milestone, completing final plans. The right-of-way acquisition process is nearly complete. Once the right-of-way acquisition is finalized, the focus will shift towards clearing activities and utility relocations to prepare the area for construction. A clearing and grubbing construction package is expected to be advertised in Q1 of 2025.
05/2024 The MOVEBR Perkins Road (Pecue - Siegen) project has achieved a significant milestone, completing final plans. The right-of-way acquisition process is nearly complete. Once the right-of-way acquisition is finalized, the focus will shift towards clearing activities and utility relocations to prepare the area for construction. A clearing and grubbing construction package is expected to be advertised in Q4 of 2024.
02/2024 The MOVEBR Perkins Road (Pecue - Siegen) project has achieved a significant milestone, completing final plans. Currently, the project is actively engaged in the process of acquiring necessary right-of-way parcels. Once the right-of-way acquisition is finalized, the focus will shift towards clearing activities and utility relocations to prepare the area for construction.
09/2023 Final plans have been completed and accepted. Right-of-way acquisition process is underway. Once right of way is acquired clearing and grubbing will begin in order for utilities to move. Clearing and grubbing should begin in quarter 2 of 2024.
05/2023 Final plans have been completed and accepted. Right-of-way acquisition process is underway. Once right of way is acquired clearing and grubbing will begin in order for utility relocations to begin.
01/2023 The Design Consultant has submitted 100% Final Plans. Right of way acquisition process is underway.
06/2022 The Design Consultant is working on completing their final design package. Wetland permit documents have been submitted. Right of way acquisitions are currently underway.
08/2021 The Design Consultant is working on completing their final design package, wetland delineation, and Right of way maps.
07/2021 The Design Consultant has prepared an updated concept report and final design is underway. A public meeting will be scheduled early in the design process.
02/2021 The Design Consultant has prepared an updated concept report. Contracting is underway with the Engineering Design Consultant. A public meeting will be scheduled early in the design process.
12/2020 The Design Consultant has prepared an updated concept report . Contracting are underway with the Engineering Design Consultant. A public meeting will be scheduled early in the design process.

 