Perkins Road (Pecue-Siegen) Project Page

Project Description: Design and construction of a widening of Perkins Road from Siegen Lane to Pecue Lane to include pedestrian facilities along the corridor.

Council District: 3, 9

Project Type: New Capacity

Current Phase: Right of Way

Design Consultant: Stantec

Project Manager: Zack Schmidt

Proposition Budget: $26,200,000

Estimated Letting Date: August 2024

Project Updates

Date Status
02/2024 The MOVEBR Perkins Road (Pecue - Siegen) project has achieved a significant milestone, completing final plans. Currently, the project is actively engaged in the process of acquiring necessary right-of-way parcels. Once the right-of-way acquisition is finalized, the focus will shift towards clearing activities and utility relocations to prepare the area for construction.
09/2023 Final plans have been completed and accepted. Right-of-way acquisition process is underway. Once right of way is acquired clearing and grubbing will begin in order for utilities to move. Clearing and grubbing should begin in quarter 2 of 2024.
05/2023 Final plans have been completed and accepted. Right-of-way acquisition process is underway. Once right of way is acquired clearing and grubbing will begin in order for utility relocations to begin.
01/2023 The Design Consultant has submitted 100% Final Plans. Right of way acquisition process is underway.
06/2022 The Design Consultant is working on completing their final design package. Wetland permit documents have been submitted. Right of way acquisitions are currently underway.
08/2021 The Design Consultant is working on completing their final design package, wetland delineation, and Right of way maps.
07/2021 The Design Consultant has prepared an updated concept report and final design is underway. A public meeting will be scheduled early in the design process.
02/2021 The Design Consultant has prepared an updated concept report. Contracting is underway with the Engineering Design Consultant. A public meeting will be scheduled early in the design process.
12/2020 The Design Consultant has prepared an updated concept report . Contracting are underway with the Engineering Design Consultant. A public meeting will be scheduled early in the design process.

 

Documents

Videos

Watch the Virtual Public Meeting Held on September 28, 2021

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.