Sherwood Forest Blvd Sidewalks (Coursey Blvd - I-12) Project Page

Construction has begun on the Sherwood Forest Sidewalks Project between I-12 and Coursey Boulevard. This project will enhance pedestrian mobility along Sherwood Forest Boulevard by adding a sidewalk on the west side of the roadway to serve this highly commercialized segment with multiple residential properties. For this project, the contractor will periodically work at night to close lanes when the impact to traffic flow is significantly less. The project is expected to be completed by the end of May 2026.

Project Description: The project will enhance pedestrian mobility along Sherwood Forest Blvd. by adding a sidewalk on the west side of the roadway. Sherwood Forest is a highly commercialized segment of roadway with multiple residential properties.

Council District: 8

Project Type: Community Enhancement

Current Phase: Right of Way

Design Consultant: GWS Engineering

Project Manager: Henok Abebe

Proposition Budget: $1,000,000

Estimated Letting Date: May 2025

Project Updates

Date Status
10/2025 NTP for construction is scheduled for October 20th.
08/2025 Construction contract executed and project ready for construction.
06/2025 The low bidder for construction has been determined, project is awaiting construction contract execution.
04/2025 The construction bid documents are prepared. Construction advertisement is anticipated in Q2 2025.
03/2025 The Design Consultant has completed 100% final plans. ROW acquisition is complete. The construction bid documents are being prepared. Construction advertisement is anticipated in Q2 2025.
12/2024 The Design Consultant has completed 100% final plans. ROW acquisition is complete. The construction bid documents are being prepared. Construction advertisement is anticipated in Q1 2025.
10/2024 The Design Consultant has completed 100% final plans. ROW acquisition is nearly complete.
05/2024 PMT review completed, consultant submitted updated Final plans & ROW Acquisition is underway.
04/2024 Final plans & ROW Mapping submitted by consultant, PMT reviewing submittals.
03/2024 Final plans submitted by consultant, PMT reviewing submittals.
02/2024 Final plans submitted by consultant, PMT reviewed plans and currently consultant working on revision of final plans according to PMT and city parish comments.
01/2024 Final plans are nearly complete by the design consultant. Required ROW acquisition is underway.
11/2023 Final plans are being developed by the consultant.
08/2023 The Design Consultant has submitted the Final Plans for review. Right-of-way acquisition services are underway.
12/2022 The Design Consultant has submitted the Final Plans for review. Right-of-way maps are being prepared.
05/2022 The 90% design submittal is complete and right of way maps are underway. Currently title abstracts are being prepared.
10/2021 The Design Consultant has submitted the Final Plans for review.
09/2021 The Design Consultant is preparing the final plans.
07/2021 PIH meeting on 7-19-21. The design Consultant is working on PIH comments. Submittal around 8-20-21.
05/2021 The Design Consultant is preparing the 60% final plan submittal. 
02/2021 The Design Consultant is preparing the 30% final plan submittal. 
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant.

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.

--->