| Date |
Status |
| 05/2026 |
Phase 1 Construction remains ongoing. Phase 2 PIH complete and preparing the 90% plan submittal.
Groom Road will be closed from Clermont St. to Plank Rd. May 6-May 20, 2026 to replace cross drain pipes that will help alleviate local flooding. Please use the detour shown in the maps and exercise caution when traveling in this area. Local traffic will be allowed past Clermont St. to access residences, Hillcrest Memorial Gardens Cemetery, Baker Funeral Home, and Sonic Drive-in Restaurant on the north side of Groom Rd. Other businesses in the area and the Advantage Charter Academy can be accessed from Plank Road. We appreciate your patience as we work to make Groom Rd. safer for all users. |
| 04/2026 |
Phase 1 Construction remains ongoing. Phase 2 Design activities are underway, with 60% comments returned to consultant. |
| 02/2026 |
The Design Consultant is preparing the 60% (plan in hand) design submittal. |
| 01/2026 |
The 60% design submittal is being reviewed by the PMT and the City-Parish. |
| 12/2025 |
Phase 1: Vegetation complete with utility relocations ongoing. Phase 2: 60% reviews complete, pending drainage comments from PMT. |
| 11/2025 |
Phase 1 Groundbreaking event held October 2025, Construction NTP will be November 17. Utility relocations are ongoing.
Phase 2 Design progressing towards 60%. |
| 10/24/2025 |
The Phase 1 construction contract has been awarded to KCR Construction, LLC and NTP is scheduled for November 17, 2025. Groundbreaking event will be held on October 28, 2025. Utility relocations are being finalized. |
| 10/01/2025 |
The Phase I project low bidder has been awarded and anticipated NTP is late December 2025. Utility relocations are ongoing. |
| 09/2025 |
The Phase I project (McHugh Road to Plank Road) bids have been opened, and the award/contracting process is underway. Anticipated NTP is late December 2025. |
| 07/2025 |
The Phase I project (McHugh Road to Plank Road) bids have been opened, and the award/contracting process is underway. Anticipated NTP is late Fall 2025 |
| 04/2025 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The construction bid documents for Phase 1 are being prepared. Construction advertisement is anticipated in Q2 2025. |
| 02/2025 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The construction bid documents for Phase 1 are being prepared. Construction advertisement is anticipated in Q3 2025. |
| 10/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The construction bid documents are being prepared. Construction advertisement is anticipated in Q4 2024. |
| 08/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. Offers are being presented to property owners for Phase I. |
| 07/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. Offers are being presented to property owners. |
| 04/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. Phase I Right of way acquisitions are underway and 100% Final Plans are nearly complete. |
| 03/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. Right of way acquisitions for Phase I are underway. Phase I Right of way acquisitions are underway and 100% Final Plans are nearly complete. |
| 02/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. Right of way acquisitions for Phase I are underway. |
| 01/2024 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The consultant is nearly complete with final plans for Phase I. Required ROW acquisitions for Phase I are underway. |
| 12/2023 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The consultant is working on final plans for Phase I. Appraisals for Required ROW for Phase I are underway. |
| 11/2023 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The Design Consultant is working on the comments from the 90% design submittal for Phase I. Right-of-way maps have been prepared and are under review. |
| 08/2023 |
Project has been split into two phases. Phase I is from McHugh intersection east to Plank Rd. Phase II is from McHugh intersection west to Main St. The Design Consultant is preparing the 90% design submittal for Phase I. ROW maps have been prepared and are under review. |
| 12/2022 |
The Design Consultant is preparing the 60% (plan in hand) design submittal. |
| 05/2022 |
The design study is complete and public meeting was held. Negotiations and contracting for the Final Design Phase are underway with the Engineering Design Consultant. |
| 05/2021 |
The Design Consultant is preparing the design study. Topographic survey and environmental investigations are complete. A public meeting will be held before the conclusion of the design study phase. |