Hidden Bike Path (College Dr - Country Club Dr) Project Page

Project Description: This project proposes to enhance mobility by improving the existing Gus Kinchen Trail bike path to upgrade safety treatments at street crossings, pedestrian and bicycle markings and signage, and possible low level "top down" lighting enhancements. This path is a neighborhood trail used by Webb Park residents connecting College Dr. to Country Club Dr.

Council District: 12

Project Type: Community Enhancement

Current Phase: Construction Procurement

Design Consultant: M.B. Design Consultants, LLC

Project Manager: Henok Abebe

Proposition Budget: $200,000

Estimated Letting Date: October 2024

Project Updates

Date Status
12/2024 Project opened bids in November and contract to be awarded to low bidder in December 2024. Construction expected to begin at end of Q1 2025.
10/2024 Project is currently under advertisement for bids. Bid opening expected in November.
09/2024 Project construction documents have been prepared and advertisement for bids is expected in early October.
06/2024 The Design Consultant submitted 100% Final Plans; Project is being prepared for bid.
05/2024 The Design Consultant is working on 90% Final Plans submittal.
03/2024 Final construction plans submitted by consultant. Project is being prepared for advertisement.
02/2024 Final Plans completed by Consultant. Construction advertisement package will be developed.
01/2024 Final plans are nearly complete by the design consultant.
11/2023 Final plans are being developed by the consultant.
08/2023 The Design Consultant is preparing final plans.
12/2022 The Design Consultant has submitted the Final Plans and they are under review.
05/2022 The Design Consultant is preparing 90% final plans.
12/2021 The Design Consultant has submitted the Preliminary Plans and they are under review.
09/2021 The Design Consultant is preparing preliminary plans.
08/2021 The Design Consultant is had submitted the revised Design Study Report on 7/22/21. Webb Park feedback by 8/12/21
07/2021 The Design Consultant is working on the Design Study Report.
12/2020 The Design Consultant is preparing the design study. 
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant.

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.