Highland at Siegen Project Page

Project Description: The intersection of Highland Rd and Siegen Ln is included in the program for additional capacity. The project will construct additional storage for cars within the intersection.

Council District: 3

Project Type: New Capacity

Current Phase: Design

Design Consultant: SJB, Inc

Project Manager: Brian Smith

Proposition Budget: $3,000,000

Estimated Letting Date: 2026

Project Updates

Date Status
09/2024 The final design of the intersection improvements is underway and the consultant is preparing 90% plans. The construction plans are expected to be completed in Q4 of 2024.
08/2024 The final design of the intersection improvements is underway. The construction plans are expected to be completed in Q4 of 2024. MOVEBR is scheduling the PIH meeting and the 404 Permit has been prepared.
05/2024 The final design of the intersection improvements is underway. The construction plans are expected to be completed in Q3 of 2024.
01/2024 The final design of the intersection improvements is underway. The construction plans are expected to be completed in Q2 of 2024.
12/2023 The final design of the intersection improvements is underway. The construction plans are expected to be completed in Q1 of 2024.
09/2023 The final design of the intersection improvements is underway. The construction plans are expected to be completed in quarter 4 of 2023.
07/2023 The final design of the intersection improvements is underway. The right-of-way acquisition process will begin in quarter 3 of 2023.
01/2023 The final design of the intersection improvements is underway. The construction plans to be completed in quarter 3 of 2023.
06/2022 The Design Consultant has completed the Design Study Phase. A public meeting for this is being scheduled for July.
10/2021 The Design Consultant is preparing the draft Design Study for review. The Design Study along with the Traffic Study will determine the modifications needed for the intersection.
08/2021 The Design Consultant is preparing the final Traffic Report and draft Design Study. Those two elements of work will determine the modifications needed for the intersection.
07/2021 The Design Consultant is preparing the final traffic study and draft design study. Those two elements of work will determine the modifications needed for the intersection.
02/2021 The Design Consultant is preparing the traffic study and draft design study. Those two elements of work will determine the modifications needed for the intersection. 
12/2020 The Design Consultant has completed survey of the project area and are beginning to work on the Design Study to developed the intersection improvements.

 