Hooper Rd (Blackwater - Joor) Project Page

Project Description: Hooper Road from Blackwater to Joor will be widened to provide additional capacity. Hooper Road is a state route (LA 408) and the DOTD is participating in the project. The design study will consider a 4-lane suburban section with pedestrian facilities as per MOVEBR Design Guidelines.

Council District: 4

Project Type: New Capacity

Current Phase: Design

Design Consultant: Sigma

Project Manager: Daniel Marks

Proposition Budget: $39,000,000

Estimated Letting Date: 2024

Project Updates

Date Status
01/2023 Development of Final plans is on-going. The right-of-way acquisition process is planned to begin in early 2023.
03/2022 Final plans are being developed. The traffic analysis is completed.
11/2021 The Design Consultant has completed the Traffic Study and currently in the final plans phase.
09/2021 The Design Consultant is preparing the traffic study with LADOTD involvement. Once complete, the project will move into final design.
07/2021 The Design Consultant is preparing the traffic study with LADOTD involvement. Once complete, the project will move into final design. A public meeting was held June 17, 2021.
06/2021 The Design Consultant is preparing the traffic study with LADOTD involvement. Once complete, the project will move into final design. A public meeting will be held June 17, 2021.
02/2021 Once the traffic study is complete, the project will move into final design. 
10/2020 The Design Consultant is preparing the traffic study with LADOTD involvement.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.