Hooper Rd (Joor - Sullivan) Project Page

Project Description: Hooper Road from Joor to Sullivan will be widened to provide additional capacity. Hooper Road is a state route (LA 408) and the DOTD is participating in the project.

Council District: 4

Project Type: New Capacity

Current Phase: Right of Way

Design Consultant: Professional Engineering Consultants Corporation

Project Manager: Daniel Marks

Proposition Budget: $11,000,000

Estimated Letting Date: 2025

Project Updates

Date Status
03/2024 Design plans are in final review. The Right-of-Way acquisition process is scheduled to begin Q2 of 2024. Utility relocations and construction activities will start after the land is acquired for the project.
01/2024 Design plans are in final review. The Right-of-Way acquisition process is scheduled to begin Q1 of 2024. Utility relocations and construction activities will start after the land is acquired for the project.
12/2023 Design plans are in final review. The Right-of-Way acquisition process is scheduled to begin Q1 of 2024. Utility relocations and construction activities will start after the land is acquired for the project.
09/2023 The Consultant is nearly complete with final plans. The Right-of-Way acquisition process is scheduled to begin quarter 4 of 2023. Utility relocations and construction activities will start after the land is acquired for the project.
06/2023 The Consultant is nearly complete with final plans. The right-of-way acquisition process is scheduled to begin in quarter 3 of 2023. Utility relocation plans are being finalized.
01/2023 The Consultant is nearly complete with final plans. The Right-of-Way acquisition process should begin in early 2023.
03/2022 Final plans are being developed. The traffic analysis is completed.
09/2021 This project is currently in the final design stage.
07/2021 The Design Consultant is preparing the traffic study with LADOTD involvement. Upon completion, the Design Consultant will move into Final Plan production. A Public Meeting was held June 17, 2021.
06/2021 The Design Consultant is preparing the traffic study with LADOTD involvement. Upon completion, the Design Consultant will move into Final Plan production. A Public Meeting will be held June 17, 2021.
02/2021 The Design Consultant is preparing the traffic study with LADOTD involvement. Upon completion, the Design Consultant will move into Final Plan production.
10/2020 The Design Consultant is preparing the traffic study with LADOTD involvement. Upon completion, negotiations and contracting will be underway with the Engineering Design Consultant to begin development of final plans.

 