McHugh Rd (Groom Rd. to Lower Zachary) Project Page

Project Description: The project includes design and construction of a new/realigned rural, two-lane roadway. The Comite bridge is being constructed by United States Army Corps of Engineers.

Council District: 1

Project Type: New Capacity

Current Phase: Construction Procurement

Design Consultant: CSRS

Project Manager: Zach Schmidt

Proposition Budget: $8,000,000

Estimated Letting Date: July 2021

Project Updates

Date Status
09/2024 The North, Phase A project has been awarded for construction. Estimated Notice to Proceed is expected by November 2024. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete in 2026.
08/2024 The North, Phase A project has been awarded for construction. Estimated Notice to Proceed is expected by November 2024. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete during 2025.
05/2024 The Design Consultant has completed the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. North Phase A is the roadway work from Lower Zachary Road to a location before the bridge approaches. This section of the project will be advertised for construction in June 2024. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete during 2025.
02/2024 The Design Consultant has completed the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. Phase A will be begin construction in 2024 once utility relocations are complete. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete by 2025.
11/2023 The Design Consultant has completed the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. Phase A will be advertised for construction once utility relocations are complete. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete by 2025.
07/2023 The Design Consultant is completing the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. Upon completion of utility relocations, Phase A will be advertised for construction. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete in 2025.
01/2023 The Design Consultant is completing the final plans for the project. Currently, utility companies are completing relocations. The northern portion of the project will be advertised for construction in early 2023, contingent upon the completion of the U.S. Army Corps of Engineers project. The remainder of the project will not be completed until after the Comite River Diversion is functional. That is anticipated to be complete by 2025.
03/2022 The Engineering Design Consultant is completing the final plans for the projects. Clearing and Grubbing construction is currently underway. The project will not be completed until after the Comite River Diversion is functional.
08/2021 The Engineering Design Consultant is completing the final plans for the projects. Clearing and Grubbing plans are completed and coordination is underway with the United States Army Corps to determine the appropriate timing for each contract to be constructed. The project will not be completed until after the Comite River Diversion is functional.
12/2020 The Engineering Design Consultant is completing the final plans for the projects. Clearing and Grubbing plans are completed and coordination is underway with the United States Army Corps to determine the appropriate timing for each contract to be constructed.

Documents

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
Clearing and Grubbing $378,423.00

Videos

Watch the Virtual Public Meeting Held on May 11, 2021

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.