| Date |
Status |
| 08/2026 |
Phase A: Barring any major issues, the contractor expects to be substantially complete by 8/14/26. Phase B: Expected to be advertised for construction in Q3 of 2026. |
| 05/2026 |
Phase A construction is underway. The contractor is working on drainage and roadway components and expects to be completed in 6 months. Phase B final plans are being prepared, and it is expected that the construction of Phase B will be advertised for construction in Q2 of 2026. |
| 04/2026 |
Phase A clearing and grubbing is underway. The roadway construction in this area will begin in March 2026. Phase B final plans are being prepared, the project will be advertised for construction in Q2 of 2026. |
| 02/2026 |
Florida Gas has completed their relocation work and the contractor for McHugh road construction will rebegin construction in February to construct Phase A of the project. Phase B final plans are being prepared and the project will let in Q2 of 2026. |
| 12/2025 |
Florida Gas will complete the relocation of their pipeline within the next few weeks as part of the Comite Diversion project. The contractor for McHugh road construction will begin to mobilize in January and February to construct Phase A of the project. |
| 11/2025 |
The North, Phase A project has begun construction. Phase A will be completed in two phases to allow for Florida Gas relocation to occur for the Comite River Diversion project. Construction is currently on hold while Florida Gas completes pipeline relocations by December 2025. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. |
| 07/2025 |
The North, Phase A project has begun construction. Phase A will be completed in two phases to allow for Florida Gas relocation to occur for the Comite River Diversion project. Florida Gas is expected to be completed by August 2025 to allow the roadway construction to continue. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. |
| 03/2025 |
The North, Phase A project has begun construction. Phase A will be completed in two phases to allow for Florida Gas relocation to occur for the Comite River Diversion project. Flordia Gas is expected to be completed by Moay 2025 to allow the roadway construction to continue. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete in 2026. |
| 12/2024 |
The North, Phase A project has been awarded for construction. Estimated Notice to Proceed is expected by November 2024. Phase A will be completed in two phases to allow for Florida Gas relocation to occur for the Comite River Diversion project. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete in 2026. |
| 09/2024 |
The North, Phase A project has been awarded for construction. Estimated Notice to Proceed is expected by November 2024. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete in 2026. |
| 08/2024 |
The North, Phase A project has been awarded for construction. Estimated Notice to Proceed is expected by November 2024. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete during 2025. |
| 05/2024 |
The Design Consultant has completed the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. North Phase A is the roadway work from Lower Zachary Road to a location before the bridge approaches. This section of the project will be advertised for construction in June 2024. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete during 2025. |
| 02/2024 |
The Design Consultant has completed the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. Phase A will be begin construction in 2024 once utility relocations are complete. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete by 2025. |
| 11/2023 |
The Design Consultant has completed the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. Phase A will be advertised for construction once utility relocations are complete. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete by 2025. |
| 07/2023 |
The Design Consultant is completing the final plans for the project for North, Phase A. Currently, utility companies are completing relocations. Upon completion of utility relocations, Phase A will be advertised for construction. The remainder of the project is contingent upon the completion of the U.S. Army Corps of Engineers project and after the Comite River Diversion is functional. That is anticipated to be complete in 2025. |
| 01/2023 |
The Design Consultant is completing the final plans for the project. Currently, utility companies are completing relocations. The northern portion of the project will be advertised for construction in early 2023, contingent upon the completion of the U.S. Army Corps of Engineers project. The remainder of the project will not be completed until after the Comite River Diversion is functional. That is anticipated to be complete by 2025. |
| 03/2022 |
The Engineering Design Consultant is completing the final plans for the projects. Clearing and Grubbing construction is currently underway. The project will not be completed until after the Comite River Diversion is functional. |
| 08/2021 |
The Engineering Design Consultant is completing the final plans for the projects. Clearing and Grubbing plans are completed and coordination is underway with the United States Army Corps to determine the appropriate timing for each contract to be constructed. The project will not be completed until after the Comite River Diversion is functional. |
| 12/2020 |
The Engineering Design Consultant is completing the final plans for the projects. Clearing and Grubbing plans are completed and coordination is underway with the United States Army Corps to determine the appropriate timing for each contract to be constructed. |