Port Hudson - Pride Road (LA 964 - LA 19) Project Page

Project Description: The proposed typical section adds paved shoulders while open ditches will remain, though reconstructed, throughout the corridor. A sidewalk will provide connectivity between LA 964 and Pin Oak Landing on both sides of Port Hudson - Pride Road.

Council District: 1

Project Type: New Capacity

Current Phase: Design Study

Design Consultant: ECM Consultants, Inc.

Project Manager: Zack Schmidt

Proposition Budget: $18,000,000

Estimated Letting Date: 2025

Project Updates

Date Status
02/2024 The MOVEBR Port Hudson Pride Project has reached a significant milestone, completing the initial design study phase. Currently, the project team is evaluating final alternatives to address transportation needs in the area. Once a design alternative is accepted by all stakeholders, the project will transition into the final design phase.
12/2023 The design consultant has completed the draft design study. Project alternatives are being evaluated before the project moves into final design.
11/2023 The design consultant has completed the design study. Project alternatives are being evaluated before the project moves into final design.
07/2023 The design consultant has completed the topographic survey and is continuing to work on the design study. Current efforts are studying the existing and proposed drainage.
01/2023 The design consultant will begin the design study work, beginning with topographic survey, in January of 2023.
06/2022 A design consultant has been selected. Scope and fee negotiations are currently underway. No design activity is underway.
12/2020 This project is in the planning phase based on prioritization. No design activity is underway.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.