Sharp Road Corridor Enhancements (Old Hammond Hwy. to Florida Blvd.) Project Page

Project Description: This project is proposed to provide access management and turning lane improvements along Sharp Rd. This project is also proposed to enhance pedestrian and bicycle mobility.

Council District: 6, 11

Project Type: Improve Existing Corridors

Current Phase: Design

Design Consultant: GOTECH

Project Manager: Nick Prudhomme

Proposition Budget: $11,000,000

Estimated Letting Date: Q3 2025

Project Updates

Date Status
09/2024 Contracting for final plan development is underway.
03/2024 A public meeting was held on February 29, 2024. Negotiations and contracting are underway with the Engineering Design Consultant to begin development of final plans.
02/2024 The project is in the preliminary design phase. A public meeting will be held on February 29, 2024.
01/2024 The project is in the preliminary design phase. A public meeting will be held in mid-February.
11/2023 The project is in the preliminary design phase.
08/2023 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
12/2022 Design Consultant has been selected and design contract is being processed. Topographic survey and design study activities will begin upon execution of the contract.
05/2022 Design Consultant selection in progress. Anticipated selection date June 2, 2022.
10/2020 This project is in the planning phase based on prioritization. No design activity is underway.