Date Status
08/2023 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
12/2022 Design Consultant has been selected and design contract is being processed. Topographic survey and design study activities will begin upon execution of the contract.
05/2022 Design Consultant selection in progress. Anticipated selection date June 2, 2022.
10/2020 This project is in the planning phase based on prioritization. No design activity is underway.