Sharp Road Corridor Enhancements (Old Hammond Hwy. to Florida Blvd.) Project Page

Project Description: This project is proposed to provide access management and turning lane improvements along Sharp Rd. This project is also proposed to enhance pedestrian and bicycle mobility.

Council District: 6, 11

Project Type: Corridor Improvements

Current Phase: Design Study

Design Consultant: GOTECH

Project Manager: Nick Prudhomme

Proposition Budget: $11,000,000

Estimated Letting Date: Q1 2025

Project Updates

Date Status
03/2024 A public meeting was held on February 29, 2024. Negotiations and contracting are underway with the Engineering Design Consultant to begin development of final plans.
02/2024 The project is in the preliminary design phase. A public meeting will be held on February 29, 2024.
01/2024 The project is in the preliminary design phase. A public meeting will be held in mid-February.
11/2023 The project is in the preliminary design phase.
08/2023 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
12/2022 Design Consultant has been selected and design contract is being processed. Topographic survey and design study activities will begin upon execution of the contract.
05/2022 Design Consultant selection in progress. Anticipated selection date June 2, 2022.
10/2020 This project is in the planning phase based on prioritization. No design activity is underway.

Documents

Photos

Videos

 Drone footage

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.