South Choctaw (Flannery - Central Thruway) Project Page

Project Description: A legacy project that was designed prior to GLP and MOVEBR. Design and construction of a four-lane roadway with sidewalks. The project will be revised based on a new drainage design and updated design guidelines.

Council District: 4

Project Type: New Capacity

Current Phase: Design

Design Consultant: Evans-Graves

Project Manager: Brian Smith

Proposition Budget: $12,000,000

Estimated Letting Date: 2022

Project Updates

Date Status
02/2021 The final plans are approximately 90% complete. Environmental permitting is underway with the United States Army Corps of Engineers.
12/2020 The final plans are approximately 90% complete. Environmental permitting is underway with the United States Army Corps.

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.