South Choctaw (Flannery - Central Thruway) Project Page

Project Description: A legacy project that was designed prior to GLP and MOVEBR. Design and construction of a four-lane roadway with sidewalks. The project will be revised based on a new drainage design and updated design guidelines.

Council District: 4

Project Type: New Capacity

Current Phase: Design

Design Consultant: Evans-Graves

Project Manager: Brian Smith

Proposition Budget: $12,000,000

Estimated Letting Date: August 2021

Project Updates

Date Status
08/2021 The Consultant is finalizing the design plans. Utilities have begun relocations within the existing ROW, roadway construction will follow once utility relocations have been completed.
07/2021 The Consultant is finalizing the design plans. Utilities will begin relocation in July with roadway construction following that activity.
05/2021 The Consultant is finalizing the design plans. Utilities will begin relocation in June with roadway construction following that activity. 
02/2021 The final plans are approximately 90% complete. Environmental permitting is underway with the United States Army Corps of Engineers.
12/2020 The final plans are approximately 90% complete. Environmental permitting is underway with the United States Army Corps.

 