South Choctaw (Flannery - Central Thruway) Project Page

Project Description: A legacy project that was designed prior to GLP and MOVEBR. Design and construction of a four-lane roadway with sidewalks. The project will be revised based on a new drainage design and updated design guidelines.

Council District: 4

Project Type: New Capacity

Current Phase: Construction

Design Consultant: Evans-Graves

Project Manager: Brian Smith

Proposition Budget: $12,000,000

Estimated Letting Date: October 2021

Project Updates

Date Status
01/2024 Construction of the project is complete.
10/2023 Construction of the project is underway. The contractor is expected to be complete during Q4 of 2023.
07/2023 Construction of the project is underway. The contractor is installing subsurface drainage throughout the corridor as the road construction continues. Single lane closures are still being used by the team to complete the construction.
01/2023 Construction of the project is underway. The contractor is installing drainage pipes throughout the corridor ahead of the road construction.
06/2022 Construction activities for the S. Choctaw widening will begin in early August.
11/2021 The utilities are being relocated within the corridor ahead of planned roadway construction. The Letting date for the road work will be November 23, 2021.
10/2021 The utilities are being relocated within the corridor ahead of planned roadway construction. The Letting date for the road work will be in late November 2021.
08/2021 The Consultant is finalizing the design plans. Utilities have begun relocations within the existing ROW, roadway construction will follow once utility relocations have been completed.
07/2021 The Consultant is finalizing the design plans. Utilities will begin relocation in July with roadway construction following that activity.
05/2021 The Consultant is finalizing the design plans. Utilities will begin relocation in June with roadway construction following that activity. 
02/2021 The final plans are approximately 90% complete. Environmental permitting is underway with the United States Army Corps of Engineers.
12/2020 The final plans are approximately 90% complete. Environmental permitting is underway with the United States Army Corps.

 

Documents

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
RJ Daigle & Sons Contractors, LLC Construction Services $5,941,233.43

Videos

Watch the Virtual Public Meeting Held on May 20, 2021