72nd Ave Sidewalks Ph I (Scenic Hwy to I-110) Project Page

Project Description: This project is proposed to reconstruct sidewalks, provide ADA compliance, and accommodate bus transit stops on each side of 72nd Avenue between Scenic Hwy. (US 61) and I-110.

Council District: 10

Project Type: Community Enhancement

Current Phase: Construction Complete

Design Consultant: PEC

Project Manager: Alex Farr

Proposition Budget: $700,000

Estimated Letting Date: March 2020

Project Updates

Date Status
09/2021 Construction is complete. Photo gallery of completed project.
10/2020 Construction is underway - Sidewalks and ADA ramps are being placed.

Documents

Photos

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
Gulf States Services, LLC Construction Services $536,016.25 Complete