Q3 2024 Progress Report

The following information is accurate through September 30, 2024.

Projects By Phase
Project Phases # of Projects in This Phase
Planning 24
Engineering Procurement 16
Design 35
Right of Way (ROW) 08
Permitting 00
Utilities 00
Construction Procurement 20
Construction 08
Construction Complete 25
Total Projects 136

Note: 72 projects were included in the original MOVEBR proposition. A number of these projects, such as ADA improvements and signalization, have been separated into specific, standalone projects for design and construction. The total number of projects listed reflects all of these and will continue to increase in the future, but will always align with the original 72 projects approved for the MOVEBR program.

 

Dollars Spent

Cumulative including administrative fees

Funding Source Dollar Amount Spent
MOVEBR $170,356,433
Green Light Program $43,865,293
State/Federal & Other Funds $59,323,573
Total $273,545,299

 

Local & Small Business Dollars Committed

Cumulative based on contracts excluded. Does not include contracts under negotiation.

Category Location Contracted Amount (%)
Local Business In EBR Parish $168,343,448 87.94%
Local Business In Louisiana $21,348,603 11.18%
Category Type Contracted Amount (%)
Small Business Minority-Owned Businesses $31,743,895 16.58%
Small Business Woman-Owned Businesses $16,776,507 8.76%
Small Business Veteran-Owned Businesses $3,127,271 1.63%
Small Business Total $51,647,673 26.97%
Small Business Target   20%

 

Project Status By Key Benefits
Key Benefit Number Planned % of Projects in Planning Phase % of Projects in Design Phase % of Projects in Construction Phase % of Projects Completed
Lane Miles of New Roadway 112.90 21.9% 57.3% 17.9% 2.9%
Lane Miles of Enhanced Roadway 124.01 22.5% 57.0% 18.3% 2.2%
Miles of Sidewalk 267.31 8.4% 79.5% 7.8% 4.3%
Miles of Bike Paths 70.48 17.1% 66.0% 16.9% 0.0%
Traffic Signals Upgraded 105 11.4% 82.9% 5.7% 0.0%
Traffic Signals Replaced 126 3.2% 33.3% 63.5% 0.0%
Miles of Fiber for Signals 84.16 0.0% 1.3% 0.1% 98.6%
New School Flashers 302 0.0% 2.6% 1.3% 96.0%

Planned value is updated per project based upon the current planned amount per key benefit. Percentages by phase are calculated based upon the summation of all projects in the MOVEBR and their appropriate Project Phase. Design includes Engineering Procurement, Design, ROW, and Utilities. Construction includes Construction Procurement and Construction. Completed indicates Project Acceptance has been reached.

 

Communication/Outreach

Public Contacts Number of Contacts
No. of Public Contacts Received* 2052
Required Responses to Public Inquiries 1857

*Questions/inquiries through website, social media, email, calls, etc. Numbers are cumulative since the program's inception.

 

Procurement

Executed Contracts by Month
Number of Contracts Executed Month
6 Oct 2023
5 Nov 2023
1 Dec 2023
9 Jan 2024
1 Feb 2024
1 Mar 2024
0 Apr 2024
9 May 2024
2 Jun 2024
3 Jul 2024
5 Aug 2024
5 Sep 2024

Contracts executed through the Office of the Mayor-President.