72nd Ave Sidewalks Ph II (I-110 to Plank Rd) Project Page

Project Description: This project proposes to construct new sidewalk, provide ADA compliance, and accommodate bus stops on 72nd Avenue between I-110 and Plank Road.

Council District: 2, 10

Project Type: Community Enhancement

Current Phase: Construction Complete

Design Consultant: Phase II - PEC; Phase III- Pivotal (Lighting)

Project Manager: Alex Farr

Proposition Budget: $600,000

Estimated Letting Date: August 2021

Project Updates

Date Status
06/2024 Construction is complete for sidewalks.

Contracting is underway for lighting design.
08/2023 Construction is complete.
12/2022 Construction is underway.
05/2022 Bids have been opened and the award/contracting process is underway. Anticipated NTP date is June, 2022
12/2021 Bids have been opened and award/contracting is underway. Anticipated NTP date is January, 2022
09/2021 Bids have been opened and award/contracting is underway.
09/2021 The project is advertised for construction. Bids will be opened 9/14/2021, subject to any addendums.
07/2021 The construction advertisement for the project is being prepared.
04/2021 The Design Consultant is preparing the 100% plan submittal.
02/2021 The Design Consultant is preparing the 90% plan submittal.
10/2020 The 60% design submittal is being reviewed by the PMT and the City-Parish.

Documents

Construction Components

Contractor Contract Description Contract Value Estimated Completion Date
Boone Services Construction Services $659,200.00 Q4 2022

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.