Beech St. / Hollywood St. Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Beech St. / Hollywood St. and the surrounding area.

Council District: 5

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Regis Infrastructure Group

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.48

Estimated Letting Date: July 2022

Contractor: The Luster Group LLC

Project Updates

Date Status
09/2024 Construction is complete.

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.

--->