Blue Grass Dr Improvements and Sidewalk Project Page

Project Description: Street/drainage improvements and sidewalk addition on Blue Grass Dr. from Cadillac St. to Fortune Addition Park.

Council District: 5

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Infinity Engineering Consultants

Project Manager: Billy Wall

Current Cost Estimate ($M): $1.00

Estimated Letting Date: October 2025

Project Updates

Date Status
11/2025 The 90% design submittal is being reviewed by the PMT
12/2023 Project is currently in the procurement phase for design services.
08/2023 This project is in the planning phase based on prioritization. No design activity is underway.

Documents

Comments