Bluebonnet Blvd Mid-Block Crossing Project Page

Project Description: Add mid-block crossing and pedestrian signal with advanced warnings near the intersection of Springpark Ave and Bluebonnet Blvd.

Council District: 3

Project Type: Call For Projects

Current Phase: Construction

Design Consultant: Vectura

Project Manager: Jolie D. Maberry

Current Cost Estimate ($M): $0.40

Estimated Letting Date: August 2024

Project Updates

Date Status
11/2025 Poles, signal cabinets, and majority of work installed, expecting pedestrian signals to be operational early November 2025. Sidewalk construction complete. Expecting construction completion by end of November 2025. Ribbon cutting event planning in progress.
10/2025 Poles, signal cabinets, and majority of work installed, but not powered on. Sidewalk construction ongoing.
04/2025 Project is in the construction phase. Signal material lead times will require construction to begin in September 2025.
03/2025 Project is in the construction phase. Signal material lead times will require construction to begin in May 2025.
12/2023 Topographic survey for project is underway.
08/2023 Negotiations and contracting are underway with the Engineering Design Consultant.