Project |
Most Recent Update (as of July 2025) |
Mt Pleasant Rd Sidewalks & Mid-block Crossing @ Zachary Youth Baseball Park (Funds Transfer) |
Consultant working on finalizing 100% Plans. |
Perkins Rd Overpass |
Design Consultant is now working on the 100% Final Plan submittal and coordinating with KCS RR. Utility relocations to begin in July / August. |
Parishwide Traffic Calming Improvements/Speed Signs |
Original construction complete, additional locations to be installed. |
Progress Rd (Blount Rd to Scotland Ave) |
The Design Consultant is performing topographic survey and preparing the design study. |
Bluebonnet Blvd. Mid-Block Crossing |
Project is in the construction phase. Signal material lead times will require construction to begin in September 2025. |
Blue Grass Dr Improvements and Sidewalk |
The 98% design submittal is being reviewed by the PMT and bid documents are being prepared. |
Goodwood Blvd Sidewalks and Bike Path |
The Design Consultant has submitted 60% final plans which are currently under review by the PMT. |
Madison Ave Sidewalks |
The Design Consultant is currently revising 100% final plans to incorporate changes to address drainage field conditions. |
Lobdell Ave/Goodwood Blvd Pedestrian Crossing |
Consultant is working towards 90% Final Plans. |
Lobdell Ave/Sevenoaks Ave Pedestrian Crossing |
Consultant is working towards 90% Final Plans. |
Glasgow near Glasgow Middle |
Consultant submitted 60% Plans and field meeting has been scheduled to assess design and utility impacts. |
Scotlandville Towncenter Plaza |
The Design Consultant submitted 60% Design Plans, which are currently under review by the PMT. |
Greenwell St Sidewalks |
Negotiations and contracting are underway with the Engineering Design Consultant. |
Cora Dr Sidewalks / Broadmoor Sidewalk and Bike Path (Cora Dr) |
Consultant is working on addressing 60% Plans comments from PMT. |
Hundred Oaks Ave Sidewalks |
Construction is underway. |
George Oneal Rd Sidewalks |
Low bidder for construction awarded, project is awaiting construction contract execution |
Lobdell Ave/Government St Roundabout Lighting |
Project is currently waiting on Entergy to complete construction of the lighting. |
Rosenwald Road from Scenic Hwy to Scotland Ave |
MOVEBR PMT is reviewing the preliminary plans submitted by the design consultant. |
Robertson Ave Sidewalks |
The Design Consultant working towards 60% Final Plans. |
Marilyn Drive Sidewalks / Broadmoor Sidewalk and Bike Path (Marilyn Dr) |
The Design Consultant is performing topographic survey and preparing the design study. |
S Harrell's Ferry Rd Bike Lanes |
Bids have been opened and the award/contracting process is underway. |
South Boulevard Trailhead Connection |
"The Design Consultant is preparing the 90% Final Plans. |
Audubon Ave Sidewalk |
Negotiations and contracting are underway with the Engineering Design Consultant. |
Pollard Pkwy. Sidewalk (Combined with Lancaster) |
The low bidder for construction has been determined, project is awaiting construction contract execution. |
Sunshine Rd (Lavey Ln to Thomas Rd) |
The Design Consultant is preparing the 60% Final Plans. |
Lancaster Ave. & Pollard Pkwy Sidewalks |
Low bidder for construction has been determined, and the project is awaiting construction contract execution. |
N Ardenwood Dr Sidewalks |
Negotiations and contracting are underway with the Engineering Design Consultant. |
Floynell Dr Sidewalk |
The Design Study has been reviewed by the PMT and the Consultant is working towards 60% Preliminary Plans. |