Clayton St. Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Clayton St. and the surrounding area.

Council District: 5, 7

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Regis Infrastructure Group

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.41

Estimated Letting Date: February 2022

Contractor: Honore Company, LLC

Project Updates

Date Status
11/2023 Construction is complete.