Downtown ADA Transition Projects

Select a project below to display on map:

Show On Map Project Name Current Phase Project Manager Design Consultant Estimated Letting Date
Main St. Area ADA Transition Project Construction Procurement Josh Olivier Bonton Associates January 2025
Laurel St. / Lafayette St. Area ADA Transition Project Construction Procurement Josh Olivier Bonton Associates January 2025
 

Main Street ADA Project Description: This project is to address ADA deficiencies in sidewalks, ramps, crosswalks, and associated construction for pedestrian movement within municipal right of ways along Main St. and the surrounding area.

Council District: 10

Project Type: ADA Transition Projects

Current Phase: Construction

Design Consultant: Bonton Associates

Project Manager: Josh Olivier

Construction Budget: $476,190.47

Estimated Letting Date: January 2025

Notice to Proceed: April 14, 2025

Contractor: Triumph Construction

Date Status
04/2025 Construction has begun and is ongoing.

Laurel & Lafayette Streets ADA Project Description: This project is to address ADA deficiencies in sidewalks, ramps, crosswalks, and associated construction for pedestrian movement within municipal right of ways along Laurel St., Lafayette Street and the surrounding area.

Council District: 10

Project Type: ADA Transition Projects

Current Phase: Construction

Design Consultant: Bonton Associates

Project Manager: Josh Olivier

Construction Budget: $476,190.47

Estimated Letting Date: January 2025

Notice to Proceed: May 5, 2025

Contractor: The Luster Group

Date Status
04/2025 Construction is underway.

Contact Us

To contact the MOVEBR program team about this project, please complete the form below.

--->