Evangeline St. Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Evangeline St. and the surrounding area.

Council District: 5, 7

Project Type: ADA Transition Projects

Current Phase: Construction

Design Consultant: Regis Infrastructure Group

Project Manager: Josh Olivier

Current Cost Estimate ($M): $0.56

Estimated Letting Date: May 2025

Contractor: TBD

Project Updates

Date Status
11/2025 Preconstruction meeting scheduled for November 3, 2025. Construction NTP to follow soon after.
10/2025 Project was combined with Evangeline St. / Alamonster Ave. ADA project. Awaiting Construction Contract execution and NTP.

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.

--->