Evangeline St. Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Evangeline St. and the surrounding area.

Council District: 5, 7

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Regis Infrastructure Group

Project Manager: Josh Olivier

Current Cost Estimate ($M): $0.56

Estimated Advertisement Date: May 2025

Contractor: ProCivil Construction, LLC

Project Updates

Date Status
08/2026 Construction is complete.
05/2026 Construction Ongoing.
12/2025 Preconstruction meeting scheduled for November 3, 2025. Construction NTP to follow soon after.
10/2025 Project was combined with Evangeline St. / Alamonster Ave. ADA project. Awaiting Construction Contract execution and NTP.

Documents

Comments

To contact the MOVEBR program team about this project or to receive updates about this project, please complete the form below.