Floynell Dr Sidewalk Project Page

Project Description: New sidewalk on one side of Floynell Dr. from Jefferson Hwy. to E. Inniswold Rd.

Council District: 11

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Meyer Engineers, LTD

Project Manager: Billy Wall

Current Cost Estimate ($M): $1.00

Estimated Advertisement Date: August 2026

Project Updates

Date Status
08/2026 Final plans received and in PMT Review. Targeting Aug '26 Advertisement.
05/2026 98% Plans reviewed and returned to consultant. Expecting final plans to be received May '26.
04/2026 The 90% design submittal reviewed and returned to consultant.
02/2026 The 90% design submittal is being reviewed by the PMT.
01/2026 The Design Consultant is preparing the 90% plan submittal.
12/2025 The Design Consultant is preparing the 90% plan submittal. Expected late December.
11/2025 The Design Consultant is preparing the 90% plan submittal.
10/2025 Consultant is working towards 60% Preliminary Plans.
08/2023 This project is in the planning phase based on prioritization. No design activity is underway.

Documents

Comments

To contact the MOVEBR program team about this project or to receive updates about this project, please complete the form below.

Powered by Cicero Government