Fuqua St. / Gracie St. Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Gracie and Fuqua St. and the surrounding area.

Council District: 7, 10

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Bonton Associates

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.41

Estimated Advertisement Date: December 2021

Contractor: Triumph Construction. LLC

Project Updates

Date Status
12/2022 Construction is complete.