Goodwood Blvd Sidewalks and Bike Path Project Page

Project Description: Provide new sidewalks & bike lanes on both sides of Goodwood Blvd. from Airline Hwy. to Sharp Rd.

Council District: 6

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Sustainable Design Solutions

Project Manager: Nick Prudhomme

Current Cost Estimate ($M): $2.00

Estimated Letting Date: December 2025

Project Updates

Date Status
11/2025 90% Plans submitted and under PMT review.
10/2025 The Design Consultant is now preparing 90% Final Plans.
04/2025 The Design Consultant is currently preparing 60% Final Plans.
09/2024 The Design Consultant is under contract and topographic survey and design study is underway.
08/2023 This project is in the planning phase based on prioritization. No design activity is underway.