Hanks Drive/Landis Drive Phase 2&3 Project Page

Project Description: This project is proposed to construct sidewalks, provide ADA compliance, and accommodate bus transit stops along Hanks Dr. from Victoria Dr. to Dickens Dr., and along Landis Dr. from Hanks Dr. to Greenwell St. (Phase 2 & 3). This project is a legacy project from Green Light Program.

Project Type: Greenlight CarryOver

Current Phase: Construction

Design Consultant: C.H. Fenstermaker & Associates

Project Manager: Alex Farr

Proposition Budget: $0

Estimated Letting Date: July 2023

Project Updates

Date Status
01/2025 Construction is complete.
12/2023 Construction is underway. Drainage, driveways and sidewalks are being placed.
11/2023 Construction is planned to begin soon. Drainage, driveways and sidewalks will be constructed.
08/2023 Bids have been opened and the award/contracting process is underway. Anticipated NTP is September 2023.
12/2022 The Design Consultant is preparing the final plans. Utility coordination is underway.
05/2022 The Design Consultant is preparing the final plans.
09/2021 The Design Consultant is preparing the final plans.

 