Hollywood St. Area ADA Transition Project (Combined to Beech St.) Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Hollywood St.

Council District: 5

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Regis Infrastructure Group

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.48

Estimated Letting Date: February 2023

Contractor: The Luster Group LLC

Project Updates

Date Status
09/2024 Construction is complete.

Documents

Comments