Jewel Newman Community Center Gateway and Signage Project

Project Description: Community enhancements in the outdoor space at Jewell Newman Community Center. Improvement will include landscaping, hardscape and minor electrical around the existing stage.

Council District: 2

Project Type: Call For Projects

Current Phase: Construction

Design Consultant: Patch, LA

Project Manager: Brendan Mott

Current Cost Estimate ($M): $0.20

Estimated Advertisement Date: August 2026

Project Updates

Date Status
05/2026 The City-Parish received no bids at the previous bid opening. The project was readvertised with a single bid received. The City-Parish is currently assessing and project remains on hold.

 