Lake Sherwood Ave/American Way Crosswalk Project

Project Description: Add a pedestrian crosswalk with pavement markings, signs and ADA accommodations

Council District: 8

Project Type: Call For Projects 2026

Current Phase: Design

Design Consultant: Grey Engineering, LLC

Project Manager: Jolie D. Maberry

Current Cost Estimate ($M): $0.05

Estimated Advertisement Date: Q1 2027

Project Updates

Date Status
05/2026 A Design Consultant has been selected and is currently in the procurement process to get the consultant under contract for design services.

 

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.