Laurel St. / Lafayette St. Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Laurel St. and Lafayette St. in the downtown area.

Council District: 10

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Bonton & Associates

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.50

Estimated Advertisement Date: January 2025

Contractor: The Luster Group LLC

Project Updates

Date Status
05/2026 Construction is complete.
02/2026 Construction is complete. Working on closeout.
01/2026 Construction is underway. Pushbuttons & components received, with installation ongoing.
11/2025 Construction is underway.

Documents

Comments

To contact the MOVEBR program team about this project or to receive updates about this project, please complete the form below.