Project Updates

Date Status
08/2026 Construction underway.
05/2026 Contractor selection complete and finalizing executed Contract. NTP underway.
03/2026 Contractor selection currently underway. Anticipated to be complete and introduced March '26.
02/2026 Design complete. Letting date scheduled for Feb '26.
01/2026 Design complete, preparing for 01/26 Advertisement.
12/2025 Consultant has submitted unsigned Final Plans and is currently under PMT review. PMT preparing for construction advertisement.
10/2025 Consultant has submitted 90% Plans and is currently under review.
01/2025 The Design Consultant has completed topographic survey and design study and currently preparing 60% Preliminary Plans.
08/2023 Negotiations and contracting are underway with the Engineering Design Consultant.