Lobdell Ave/Government St Roundabout Lighting Project Page

Project Description: Add street & pedestrian lighting at the Lobdell Ave./Government Blvd. Roundabout.

Council District: 11

Project Type: Call For Projects

Current Phase: Construction

Design Consultant: Marrero Couvillion Assoc

Project Manager: Billy Wall

Current Cost Estimate ($M): $0.30

Estimated Letting Date: October 2025

Project Updates

Date Status
11/2025 Lighting installation completed by Entergy.
10/2025 Project is currently waiting on Entergy to complete construction of the lighting.
12/2024 We are currently waiting on Entergy to begin construction of the lighting.
08/2023 Negotiations and contracting are underway with the Engineering Design Consultant.