Madison Ave Sidewalks Project Page

Project Description: Provide new sidewalks on both sides of Madison Ave. from N. 15th St. to N. 18th St. Also, no littering signage.

Council District: 10

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Southern Shores Eng.

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.60

Estimated Advertisement Date: June 2026

Project Updates

Date Status
09/2026 Bids were opened and contract was awarded. Targeting Oct '26 Construction Start.
05/2026 Design is complete, with Bid Documents being drafted. Targeting May '26 Construction Advertisement.
04/2026 Design is complete, with Bid Documents being drafted.
02/2026 Design Submittal comments returned to Consultant. Bid Docs in review.
01/2026 Design Submittal received and reviewed Dec '26.
12/2025 Design Submittal received from Consultant November '25. Routing for review.
11/2025 The Design Consultant is currently revising 100% final plans to incorporate changes to address drainage field conditions. Expecting submittal early November 2025.
12/2024 The Design Consultant is currently preparing 100% final plans.
08/2023 Negotiations and contracting are underway with the Engineering Design Consultant.

Documents

Comments

To contact the MOVEBR program team about this project or to receive updates about this project, please complete the form below.