Main Street Area ADA Transition Project Page

Project Description: This project is to address deficiencies in sidewalks, ramps, crosswalks and associated construction for pedestrian movement within municipal rights-of-way along Main St. in the downtown area.

Council District: 10

Project Type: ADA Transition Projects

Current Phase: Construction Complete

Design Consultant: Bonton Associates

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.66

Estimated Advertisement Date: January 2025

Notice to Proceed: April 14, 2025

Contractor: Triumph Construction

Project Updates

Date Status
05/2026 Construction is complete.
04/2026 Construction is underway. Pushbutton installation ongoing with an anticipated completion in Q1 2026.
12/2025 Construction is underway.