Nicholson Dr Segment 1 (Brightside - Gourrier) Project Page

Project Description: Widen Nicholson Dr. from reconstructed Brightside Lane to Gourrier Road as a 4-lane suburban road. This is a Road Transfer project and will use federal dollars. The NEPA process is being followed. The DOTD continues to manage the project and will provide construction administration and construction engineering and inspection services.

Council District: 12

Project Type: New Capacity

Current Phase: Design

Design Consultant: Forte & Tablada Inc.

Project Manager: Zack Schmidt

Proposition Budget: $21,000,000

Estimated Letting Date: 2024

Project Updates

Date Status
12/2022 The design consultant has completed the 60% final construction plans. The Design Engineer has also submitted final Right of Way maps for LADOTD to accept and begin the acquisition process. Utility agreements are being completed to relocate utilities along the corridor which may be in conflict with the proposed improvements.
05/2022 The Design Engineer is working on developing final Right of Way maps and construction documents.
08/2021 The Design Engineer is working on developing final drawings and documents.
04/2021 The Consultant is beginning the update to the NEPA Categorical Exclusion document. The Design Engineer is working on developing preliminary plans. Following the completion of the updates, the final plan process can continue.
 12/2020 The Environmental Consultant contract is pending execution. This contract will allow for updates to the NEPA documentation. Following the completion of the updates, the final plan process can continue.

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.