North Blvd Corridor Enhancement (I-110 - Foster/Florida) Project Page

Project Description: This project proposes to increase usership by enhancing mobility with Complete Streets features throughout the limits of the corridor. The MOVEBR Enhancement Project Managers will work with selected consultants for this project and for Florida Blvd projects to coordinate concepts.

Council District: 6, 7

Project Type: Improve Existing Corridors

Current Phase: Design

Design Consultant: Evans-Graves

Project Manager: Jolie D. Maberry

Proposition Budget: $15,000,000

Estimated Letting Date: 2024

Project Updates

Date Status
12/2022 The Design Consultant is finalizing the design study. A public meeting will be held on 12/15/2022.
05/2022 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
10/2021 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
09/2021 The Design Consultant is preparing the design study. Field work for topographic survey is complete. A public meeting will be held at the conclusion of the design study phase.
05/2021 The Design Consultant is preparing the design study and performing topographic survey field work. A public meeting will be held at the conclusion of the design study phase.
01/2021 Negotiations with the selected Engineering Design Consultant have been finalized and contract is being processed.  Upon execution of contract, a notice to proceed will be issued.
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant

 