North Blvd Corridor Enhancement (I-110 - Foster/Florida) Project Page

Project Description: This project proposes to increase usership by enhancing mobility with Complete Streets features throughout the limits of the corridor. The MOVEBR Enhancement Project Managers will work with selected consultants for this project and for Florida Blvd projects to coordinate concepts.

Council District: 7, 10

Project Type: Improve Existing Corridors

Current Phase: Design

Design Consultant: Evans-Graves

Project Manager: Jolie D. Maberry

Proposition Budget: $15,000,000

Estimated Letting Date: April 2025

Project Updates

Date Status
12/2024 Design Consultant working towards 90% Final Plans and Required Right-of-Way mapping.
06/2024 Design Consultant working towards 90% Final Plans.
02/2024 Design Consultant working towards 60% Final Plans.
01/2024 The 30% design submittal is being reviewed by the PMT
11/2023 Final plans are being developed by the consultant.
08/2023 Negotiations and contracting are underway with the Engineering Design Consultant to begin development of final plans.
12/2022 The Design Consultant is finalizing the design study. A public meeting will be held on 12/15/2022.
05/2022 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
10/2021 The Design Consultant is preparing the design study. A public meeting will be held at the conclusion of the design study phase.
09/2021 The Design Consultant is preparing the design study. Field work for topographic survey is complete. A public meeting will be held at the conclusion of the design study phase.
05/2021 The Design Consultant is preparing the design study and performing topographic survey field work. A public meeting will be held at the conclusion of the design study phase.
01/2021 Negotiations with the selected Engineering Design Consultant have been finalized and contract is being processed.  Upon execution of contract, a notice to proceed will be issued.
10/2020 Negotiations and contracting are underway with the Engineering Design Consultant

 

Documents

Comments

To contact the MOVEBR program team about this project, please complete the form below and a member of our team will get in touch with you shortly.