Parishwide ADA Transition Projects

Project Description: This project is to transition existing pathways, sidewalks, ramps, crosswalks, and associated facilities into a more accessible transportation network for all pedestrian users within municipal rights-of-way.  This project has been organized into 21 specific subprojects identified below.

Council District: Parishwide

Project Type: Community Enhancement

Proposition Budget: $10,000,000

 Project Components

Show On Map Project Name Current Phase Project Manager Design Consultant Estimated Letting Date
Florida Street ADA Compliance Project Design Blake Guidry SJB March 2021
Fuqua St. / Gracie St. Area ADA Transition Project Engineering Procurement Blake Guidry Bonton & Associates Q3 2021
Fairfields Ave. Area  ADA Transition Project Engineering Procurement Blake Guidry Bonton & Associates 2022
Evangeline St. (West) Area  ADA Transition Project Engineering Procurement Blake Guidry Bonton & Associates 2022
Chippewa St. Area ADA Transition Project Engineering Procurement Blake Guidry Civil Solutions CG July 2021
Winbourne Ave. Area ADA Transition Project Engineering Procurement Blake Guidry Civil Solutions CG Q4 2021
Mohican St. Area ADA Transition Project Engineering Procurement Blake Guidry Civil Solutions CG 2022
Clayton St. Area ADA Transition Project Engineering Procurement Blake Guidry Regis Infrastructure Group August 2021
Beech St. Area ADA Transition Project Engineering Procurement Blake Guidry Regis Infrastructure Group Q4 2021
Hollywood St. Area ADA Transition Project Engineering Procurement Blake Guidry Regis Infrastructure Group 2022
Evangeline St. - Scenic Hwy. Area ADA Transition Project Planning Jason Crain TBD 2023
Evangeline St. / Alamonster Ave. Area ADA Transition Project Planning Jason Crain TBD 2023
Main St. Area ADA Transition Project Planning Jason Crain TBD 2024
Evangeline St. Area ADA Transition Project Planning Jason Crain TBD 2023
Laurel St. / Lafayette St. Area ADA Transition Project Planning Jason Crain TBD 2023
North Blvd. Area ADA Transition Project Planning Jason Crain TBD 2024
South Blvd. Area ADA Transition Project Planning Jason Crain TBD 2024
East Blvd. Area ADA Transition Project Planning Jason Crain TBD 2024
W. McKinley St. / Aster St. Area ADA Transition Project Planning Jason Crain TBD 2025
Choctaw Dr. Area ADA Transition Project Planning Jason Crain TBD 2024
Douglas Ave. Area ADA Transition Project Planning Jason Crain TBD 2024
 