Progress Rd (Blount Rd to Scotland Ave) Project Page

Project Description: Complete connectivity by adding missing sidewalks on both sides of Progress Rd. from Blount Rd. to Scotland.

Council District: 2

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Quality Engineering & Surveying

Project Manager: Billy Wall

Current Cost Estimate ($M): $1.80

Estimated Letting Date: Q2 2026

Project Updates

Date Status
11/2025 The Design Consultant is preparing the 50% (hydraulic) design submittal.
10/2025 Design Study submitted by Consultant and reviewed by PMT. Railroad coordination has begun near LA 19 intersection.
03/2025 Project is in the Design Study Phase.
09/2024 Project is currently in the procurement phase for design services.
08/2023 This project is in the planning phase based on prioritization. No design activity is underway.