Rosenwald Road from Scenic Hwy to Scotland Ave Project Page

Project Description: New sidewalks on both sides of Rosenwald Rd. from Scenic Hwy. to Scotlandville Ave.

Council District: 2

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Bonton Associates

Project Manager: Henok Abebe

Current Cost Estimate ($M): $1.20

Estimated Letting Date: January 2026

Project Updates

Date Status
11/2025 90% Final Plans received and under PMT review.
10/2025 Design consultant working on 90% Final Plans. Railroad coordination underway.
12/2024 The Design Consultant is under contract and topographic survey and design study is underway.
08/2023 This project is in the planning phase based on prioritization. No design activity is underway.