S. Harrell's Ferry Rd. Bike Lanes

S. Harrell’s Ferry Road Construction Update - 12/08/25

Due to changing weather and temperature conditions, construction on the S. Harrell’s Ferry Road Bike Lanes is continuing during daylight hours. This is a moving operation with restriping work underway generally starting at S. Sherwood Forest Boulevard to O’Neal Lane.

The MOVEBR program will provide updates as they are available.

Please drive safely and exercise caution when traveling through a construction zone.

Project Description: Narrow existing travel lanes to provide for a bike lane by restriping pavement markings along S. Harrell’s Ferry Rd. from Sherwood Forest Blvd. to O’Neal Ln.

Council District: 8

Project Type: Call For Projects

Current Phase: Construction

Design Consultant: Bonton Associates

Project Manager: Alex Farr

Current Cost Estimate ($M): $1.20

Estimated Letting Date: May 2025

Project Updates

Date Status
12/2025 Construction NTP initiated with 12/25 start. Landscape being expedited, with striping operations ongoing.
11/2025 Construction NTP scheduled for November 10, 2025. Preconstruction meeting held. Nighttime striping work planned.
10/2025 Currently coordinating an NTP date with the Contractor.