S Harrell's Ferry Rd Multi-Use Path (O'Neal Ln - Woodlake Dr) Project Page

Project Description: The project will enhance pedestrian and bicycle mobility along S. Harrell’s Ferry Rd. by adding a multi-use path on the south side of the roadway. This portion of S. Harrell’s Ferry Rd. is mainly residential with two schools located along the route.

Council District: 9

Project Type: Community Enhancement

Current Phase: Design

Design Consultant: GOTECH (Survey), Bonton Associates (Design)

Project Manager: Alex Farr

Proposition Budget: $1,400,000

Estimated Letting Date: 2026

Project Updates

Date Status
10/2024 Final plans have been paused in order to resolve utility conflicts. May require revised alternative design.
11/2023 Final plans are being developed by the consultant.
08/2023 The Design Consultant has submitted the 90% final plans and they are under review. Utility relocation coordination is underway.
12/2022 The Design Consultant has submitted the 60% final plans and they are under review.
05/2022 The Design Consultant is preparing the 60% (plan in hand) design submittal.
12/2021 Field work for topographic survey is complete. The Design Study is being reviewed by the PMT and City/Parish.
09/2021 Field work for topographic survey is complete. The Design Consultant is preparing the Design Study.
05/2021 Field work for topographic survey is complete. Negotiations with the selected Engineering Design Consultant have been finalized and contract is being processed. Upon execution of contract, a notice to proceed will be issued.
02/2021 The Surveying Consultant is preparing the topographic survey.
10/2020 Negotiations and contracting are underway with the Surveying Consultant.