South Boulevard Trailhead Connection Project Page

Project Description: Connect existing South Blvd. sidewalk & S. River Rd. MUP over RR tracks to levee trailhead & provide wayfinding/signage and beautification.

Council District: 10

Project Type: Call For Projects

Current Phase: Design

Design Consultant: Regis Infrastructure Group

Project Manager: Alex Farr

Current Cost Estimate ($M): $0.50

Estimated Advertisement Date: September 2026

Project Updates

Date Status
09/2026 Coordination with Railroad and LADOTD for approval of crossing. Targeting Sep '26 Advertisement.
05/2026 RR Agreement signed by C-P and final plans received. Bid doc review underway.
01/2026 Design Submittal received and in review. RR Agreement signed by C-P and submitting final plans once agreement is FE.
12/2025 Design Submittal received from Consultant November '25. Routing for review.
11/2025 Consultant working towards 100% Final Plans. Railroad coordination is underway.
01/2025 The Design Consultant is preparing 60% Preliminary Plans.
08/2023 Negotiations and contracting are underway with the Engineering Design Consultant.

Documents

Comments

To contact the MOVEBR program team about this project or to receive updates about this project, please complete the form below.